Click the image below to see the timeline for the project:
Click the image below to see the governance for the delivery of the project:
Steering group Terms of Reference
Please click the link below to view the steering groups terms of reference:
SR Steering Group Terms of Reference vf
The programme to select the team
Milestone | Date |
Advertisement for the team (OJEU Notice) | 21 November 2013 |
Community workshop | 28 November 2013 |
Bidders Day | 04 December 2013 |
Community wider stakeholder meeting | 18 December 2013 |
Deadline for clarification questions | 18 December 2013 |
Lambeth Business Questionnaires return deadline | 7 January 2014 |
Questionnaire evaluation and shortlisting | 7 Jan – 24 Jan 2014 |
Invitation to Tender issued | 27 January 2014 |
Direction of Travel meetings | w/c 10 February 2014 |
Community workshops | w/c 10 February 2014 |
Final Tenders returned | 7 March 2014 |
Interviews | w/c 17 March 2014 |
Evaluation | 28 March 2014 |
Procurement Board 1 | tbc |
Notifications | 15 April 2014 |
Contract Award | 25 April 2014 |
Indicative Delivery Programme
Stage 1 | Timing |
Develop bespoke financial model for testing scenarios | June 2014 |
Agree preferred legal structure | July 2014 |
Agree preferred funding model | July 2014 |
Agree preferred procurement strategy | July 2014 |
Planning application submitted | January 2015 |
Stage 2 | Timing |
Planning consent obtained | June 2015 |
Contractor procured | July 2015 |
Conclusion of building contract | April 2017 |
Handover of buildings | April 2017 |
Recent Comments