Timeline & Governance

Posted By on Dec 14, 2013 |


Click the image below to see the timeline for the project:

Click the image below to see the governance for the delivery of the project:

Steering group Terms of Reference

Please click the link below to view the steering groups terms of reference:

SR Steering Group Terms of Reference vf

The programme to select the team

Milestone Date
Advertisement for the team (OJEU Notice) 21 November 2013
Community workshop 28 November 2013
Bidders Day 04 December 2013
Community wider stakeholder meeting 18 December 2013
Deadline for clarification questions 18 December 2013
Lambeth Business Questionnaires return deadline 7 January 2014
Questionnaire evaluation and shortlisting 7 Jan  – 24 Jan 2014
Invitation to Tender issued 27 January 2014
Direction of Travel meetings w/c 10 February 2014
Community workshops w/c 10 February 2014
Final Tenders returned 7 March 2014
Interviews w/c 17 March 2014
Evaluation 28 March 2014
Procurement Board 1 tbc
Notifications 15 April 2014
Contract Award 25 April 2014

Indicative Delivery Programme

Stage 1 Timing
Develop bespoke financial model for testing scenarios June 2014
Agree preferred legal structure July 2014
Agree preferred funding model July 2014
Agree preferred procurement strategy July 2014
Planning application submitted January 2015
Stage 2 Timing
Planning consent obtained June 2015
Contractor procured July 2015
Conclusion of building contract April 2017
Handover of buildings April 2017